| Description
of work done |
Upgrading and
refurbishment of data centre electrical supplies
including standby and final equipment connection
services
|
| Results
of work done |
- 2.5 times data connection capacity
- Continuity of existing services during
refurbishment
- Improved air conditioning for data
and staff areas
- Multi phase connection capability
- Improved fire protection coverage
- Completion to plan
|
|
|
|
Main Features
• SCAS NHS client
• Client 'Statement of Requirements'
• Itd survey and report
• M&E plus associated builders work
• Electrical supply upgrade
• 275 KVA diesel generator
• 150 KVA N+1 UPS system
• 250KVA auto changeover
• UPS bypass for maintenance
• Duplicate data supplies
• Data room air conditioning
• External condensers
• Internal AHU cabinets
• Fire suppression
|
|