Kenwood Expansion

Kenwood Expansion
  • Multiple phased project in the Kenwood site located in New Lane, Havant
  • Phase 1 consisted of the redevelopment of Unit 10, a standalone 1000m2 single storey warehouse, into the new Kenwood, Braun and Delonghi outlet store, academy training facility, the UK Service Centre and a 200 person capacity auditorium.
  • The whole building is fully air conditioned and features high efficiency LED lighting throughout, as well as an advanced lighting control system within the auditorium.
  • Phase 2 involves a newly constructed staff cafeteria and kitchen at ground floor level, accompanied by numerous meeting rooms and a large open plan office area suitable for up to 120 people, at first floor level.
  • Phase 3 consists of several areas throughout the main Kenwood building, including new test kitchen, Braun showroom, meeting rooms, cellular offices, electronic lab and break-out spaces.
  • Multiple mechanical heating, cooling and ventilation systems expanded and combined into the clients existing controls system.
  • Liaison with specialist design contractors including Audio Visual and Kitchen Caterers to ensure a coordinated and harmonious project delivery.